“Quinbrook’s solar and storage developer Primergy has chosen the equipment and construction partners for its US$1.2 billion Gemini Project in Nevada, US, which will have a 1,416MWh battery energy storage system (BESS).
Kiewit Power Constructors Co. will be the Gemini project’s engineering, procurement and construction (EPC) partner and IHI Terrasun Solutions will deliver and integrate the BESS. The project is expected to be completed in late 2023 and start operations soon after.
Primergy says the BESS will have a capacity of 1,416MWh, making it easily one of the largest solar-plus-storage projects in the US and, by extension, the world.”
read the entire article
Murray, Cameron. Energy Storage 3 March 2022.