“Wiltshire Council has approved Eden Renewables’ 49.9MW Forest Gate solar farm, which includes collocated battery energy storage.
The council approved the site by a majority vote of six to three.
Forest Gate solar farm will be built on a site next to the A4 in Wiltshire, east of Chippenham, and connected to the Chippenham sub-station, where it has already secured a grid connection.
“We are pleased that Forest Gate solar farm has been approved – the project has been well supported both in the local community and across Wiltshire,” said Ross Wolhuter, development manager, Eden Renewables.”
read the entire article
Lempriere, Molly. Solar Power Portal 8 March 2023.