“Despite the impact of the pandemic, the New York Power Authority’s Smart Path Moses-Adirondack rebuild continues to roll along.
During Friday’s ribbon-cutting ceremony at the Massena Intake, Power Authority President and Chief Executive Officer Gil Quiniones said the project was about one-third complete.
“We’re rebuilding what we call the Moses-Adirondack line, which starts from here all the way down to the Adirondacks, about 86 miles we’re rebuilding. I’m going to be visiting that project today. Patricia Lombardi, our head of engineering and management is here with me today. We have completed a third of that project,” Mr. Quiniones said.
.
.
.
.
It also includes rebuilding and expanding several substations along the impacted transmission corridor.”
read the entire article
Beckstead, Bob. NNY360 2021 07 26, 2021.
NYPA Transmission Map
https://www.governor.ny.gov/sites/default/files/atoms/files/GILLSMPT_map.pdf#_blank