“Dear Mr. Reilly:
We are in receipt of the January 31, 2020 comment response letter, revised FEAF, Visual Assessment Report with maps and Site Plan set dated revised January 28, 2020 all as prepared by Environmental Design Partnership, LLP. The project involves the construction of a 7.5 MW DC solar array with solid state battery storage at 709 Van Epps Road (tax map id 51.‐1‐13.2). Based on a review of the documents, we have the following comments:
SWPPP
2. The “Pervious Gravel Access Road Section Details”in the plans as provided 01/29/2020 does not conform to the Pervious Limited Use Pervious Access Road Detail as purported sanctioned by David Gasper, NYSDEC for use on Solar Field sites”
(this is appears to be identical road detail as used on Oak Hill Solar 1, LLC and Oak Hill Solar 2, LLC as reviewed by Doug Cole of Prime AE. Mr. Cole did not idicate a problem at Oak Hill Solar 1,500 foot long access road.)
read the letter PDF
Doug Cole, Prime AE February 11, 2020.